Annex I - Categories of activities referred to in Article 10

Comparing 06/01/2011 → 04/08/2024: 4 added, 2 removed, 6 changed Close comparison

The threshold values given below generally refer to production capacities or outputs. Where several activities falling under the same activity description containing a threshold are operated in the same installation, the capacities of such activities are added together. For waste management activities, this calculation shall apply at the level of activities 5.1, 5.3(a) and 5.3(b).

The Commission shall establish guidance on:

the relationship between waste management activities described in this Annex and those described in Annexes I and II to Directive 2008/98/EC; and

the interpretation of the term ‘industrial scale’ regarding the description of chemical industry activities described in this Annex.

1. Energy industries

1.1. | Combustion of fuels in installations with a total rated thermal input of 50 MW or more

1.2. | Refining of mineral oil and gas

1.3. | Production of coke

1.4. | GasificationGasification, liquefaction or liquefactionpyrolysis of:

2. Production and processing of metals

2.1. | Metal ore (including sulphide ore) roasting or sintering

2.2. | Production of pig iron or steel (primary or secondary fusion) including continuous casting, with a capacity exceeding 2,5 tonnes per hour

2.3. | Processing of ferrous metals:

2.4. | Operation of ferrous metal foundries with a production capacity exceeding 20 tonnes per day

2.5. | Processing of non-ferrous metals:

2.6. | Surface treatment of metals or plastic materials using an electrolytic or chemical process where the volume of the treatment vats exceeds 30 m3

2.7. | Manufacture of batteries, other than exclusively assembling, with a production capacity of 15 000 tonnes of battery cells (cathode, anode, electrolyte, separator, capsule) or more per year.

3. Mineral industry

3.1. | Production of cement, lime and magnesium oxide:

3.2. | Production of asbestos or the manufacture of asbestos-based products

3.3. | Manufacture of glass including glass fibre with a melting capacity exceeding 20 tonnes per day

3.4. | Melting mineral substances including the production of mineral fibres with a melting capacity exceeding 20 tonnes per day

3.5. | Manufacture of ceramic products by firing, in particular roofing tiles, bricks, refractory bricks, tiles, stoneware or porcelain with a production capacity exceeding 75 tonnes per day and/or with a kiln capacity exceeding 4 m^{3} and with a setting density per kiln exceeding 300 kg/m^{3}with:

3.6. | Extraction including on-site treatment operations, such as comminution, size control, beneficiation and upgrading, of the following ores on an industrial scale: bauxite, chromium, cobalt, copper, gold, iron, lead, lithium, manganese, nickel, palladium, platinum, tin, tungsten and zinc.

4. Chemical industry

For the purpose of this section, production within the meaning of the categories of activities contained in this section means the production on an industrial scale by chemical or biological processing of substances or groups of substances listed in points 4.1 to 4.6

4.1. | Production of organic chemicals, such as:

4.2. | Production of inorganic chemicals, such as: ▼M1 ▼B

4.3. | Production of phosphorous-, nitrogen- or potassium-based fertilisers (simple or compound fertilisers)

4.4. | Production of plant protection products or of biocides

4.5. | Production of pharmaceutical products including intermediates

4.6. | Production of explosives

5. Waste management

5.1. | Disposal or recovery of hazardous waste with a capacity exceeding 10 tonnes per day involving one or more of the following activities:

5.2. | Disposal or recovery of waste in waste incineration plants or in waste co-incineration plants:

5.3. |

5.3. | When the only waste treatment activity carried out is anaerobic digestion, the capacity threshold for this activity shall be 100 tonnes per day.

5.4. | Landfills, as defined in Article 2(g) of Council Directive 1999/31/EC of 26 April 1999 on the landfill of waste (^{40}),(^{24}), receiving more than 10 tonnes of waste per day or with a total capacity exceeding 25 000 tonnes, excluding landfills of inert waste

5.5. | Temporary storage of hazardous waste not covered under point 5.4 pending any of the activities listed in points 5.1, 5.2, 5.4 and 5.6 with a total capacity exceeding 50 tonnes, excluding temporary storage, pending collection, on the site where the waste is generated

5.6. | Underground storage of hazardous waste with a total capacity exceeding 50 tonnes

6. Other activities

6.1. | Production in industrial installations of:

6.2. | Pre-treatment (operations such as washing, bleaching, mercerisation)mercerisation), dyeing or dyeingfinishing of textile fibres or textiles where the treatment capacity exceeds 10 tonnes per dayday.

6.3. | Tanning of hides and skins where the treatment capacity exceeds 12 tonnes of finished products per day

6.4. |

6.6. | Intensive rearing of poultry or pigs:

6.5. | Disposal or recycling of animal carcasescarcasses or animal wasteby-products with a treatment capacity exceeding 10 tonnes per dayday.

6.6. | Electrolysis of water for production of hydrogen where the production capacity exceeds 50 tonnes per day.

6.7. | Surface treatment of substances, objects or products using organic solvents, in particular for dressing, printing, coating, degreasing, waterproofing, sizing, painting, cleaning or impregnating, with an organic solvent consumption capacity of more than 150 kg per hour or more than 200 tonnes per year

6.8. | Production of carbon (hard-burnt coal) or electrographite by means of incineration or graphitisation

6.9. | Capture of CO2 streams from installations covered by this Directive for the purposes of geological storage pursuant to Directive 2009/31/EC

6.10. | Preservation of wood and wood products with chemicals with a production capacity exceeding 75 m3 per day other than exclusively treating against sapstain

6.11. | Independently operated treatment of waste water not covered by Directive 91/271/EEC and discharged by an installation covered by Chapter II

Official text · consolidated version 04/08/2024 (in force) Open full page ↗