Open on EUR-Lex ↗
◷
New version applies from 30/01/2027 — introduced by Commission Delegated Regulation (EU) 2026/269. 173 provisions change. Article 125 changes in this version: compare with the current text.

Article 125 - Subsidence risk sub-module

Article 125
Subsidence risk sub-module

1.The capital requirement for subsidence risk shall be equal to the loss in basic own funds of insurance and reinsurance undertakings that would result from an instantaneous loss of an amount that, without deduction of the amounts recoverable from reinsurance contracts and special purpose vehicles, is equal to the following:

L_{(\mathrm{subsidence})} = \sqrt{\sum_{(i,j)} \mathrm{Corr}_{(\mathrm{subsidence},i,j)} \cdot \mathrm{WSI}_{(\mathrm{subsidence},i)} \cdot \mathrm{WSI}_{(\mathrm{subsidence},j)}}

where:

(a)

the sum includes all possible combinations of risk zones (i,j) of France set out in Annex IX;

(b)

Corr(subsidence,i,j) denotes the correlation coefficient for subsidence risk in risk zones i and j set out in Annex XXVI;

(c)

WSI(subsidence,i) and WSI(subsidence,j) denote the weighted sums insured for subsidence risk in risk zones i and j of France set out in Annex IX.

2.For all subsidence zones the weighted sum insured for subsidence risk in a particular risk zone i of France set out in the Annex IX shall be equal to the following:

WSI (subsidence,i) = 0,0005 · W (subsidence,i) · SI (subsidence,i)

where:

(a)

W(subsidence,i) denotes the risk weight for subsidence risk in risk zone i set out in Annex X;

(b)

SI(subsidence,i) denotes the sum insured of the insurance or reinsurance undertaking for lines of business 7 and 19 as set out in Annex I in relation to contracts that cover subsidence risk of residential buildings in subsidence zone i.

Where the amount determined for a particular risk zone in accordance with the first subparagraph exceeds an amount (referred to in this subparagraph as ‘the lower amount’) equal to the sum of the potential losses, without deduction of the amounts recoverable from reinsurance contracts and special purpose vehicles, that the insurance or reinsurance undertaking could suffer for subsidence risk in that risk zone, taking into account the terms and conditions of its specific policies, including any contractual payment limits, the insurance or reinsurance undertaking may, as an alternative calculation, determine the weighted sum insured for subsidence risk in that risk zone as the lower amount.

Official text · consolidated version 14/11/2024 (in force) Open full page ↗